How SPLIT days work
An employee on Shared Parental Leave can work up to 20 days during that leave [1]. The work does not bring the leave to an end, the limit applies per employer, and the days worked do not extend the total length of the leave. Any work done on a day, even an hour, counts as a whole SPLIT day. Work includes training and any activity to keep in touch with the workplace, but reasonable contact, such as a call to discuss the return to work, does not use up a day [2].
Neither side can insist. The employer cannot require the employee to work a SPLIT day, and the employee has no right to work one [2].
SPLIT days and KIT days
Keeping in touch (KIT) days belong to maternity leave, adoption leave and Bereaved Partner's Paternity Leave, with a limit of 10. SPLIT days belong to Shared Parental Leave and come on top of those 10 [1]. A mother who works 10 KIT days during maternity leave and then switches to Shared Parental Leave can therefore work up to 20 further SPLIT days. Each parent has their own entitlement of 20 SPLIT days [3].
The rules for KIT days are covered in the article on KIT days during maternity leave.
Pay for SPLIT days
The employee is entitled to be paid for work on a SPLIT day, at a rate set by the contract or agreed with the employer, and still receives Statutory Shared Parental Pay for that week [3]. ShPP for 2026-27 is £194.32 a week or 90% of average weekly earnings, whichever is lower [4].
What the employer must do
- Agree the dates, the work and the rate of pay before each SPLIT day, and confirm it in writing.
- Keep a running count per employee and per employer, since the regulations allow no more than 20 SPLIT days [2].
- Record the pay for the day alongside ShPP in the same pay period.
Booking and notice rules for the leave itself are set out in the guide to Shared Parental Leave.
Common mistakes
- Treating a half day or a training session as half a SPLIT day.
- Counting KIT days worked during maternity leave against the 20 SPLIT days.
- Paying only ShPP for a week in which a SPLIT day was worked.